1. The proposal was forwarded by the South DMC (online) for consideration by the Commission.
2. The Commission approved the plans in respect of Redevelopment of Integrated Exhibition cum Convention Centre (IECC) at its meeting held on June 14, 2017.
3. The building plan proposal of NOC for completion (Part) for exhibition hall (nos. A3, A4 and A5) received (online) at the completion stage was scrutinised and the following observations are given:
a) The Commission observed that elevations and sections were found to be missing in the submission made for NOC. Although, the submitted photographs depict the overall architecture and urban character for Commission’s understanding.
b) Thus NOC for completion (part) is accepted (considering time-sensitivity for use of project of national importance) and it shall be ensured, that for all future NOC completion requests, the submission shall be complete (in all respect) for consideration by the Commission.